Ferretti Plans 5 Ancona Sheds as Superyacht Segment Books No Orders
Ferretti plans five Ancona sheds under an almost €30 million plan, the first due in 2028, and its superyacht segment booked no orders through September.
Ferretti Group has announced an investment plan of almost €30 million that includes five new sheds for building superyachts in Ancona, Italy. The company said on November 18 that the sheds will double its capacity to build semi-custom steel and aluminum superyachts, and that the first of them will open in 2028.
The sheds will go up on part of the former Tubimar site in Ancona’s port, where a fire destroyed the old industrial buildings in 2020. The port authority has given Ferretti a concession on 16,175 square meters (about 174,100 square feet) of the site, and demolition of what the fire left began on November 23.
Three weeks before the announcement, Ferretti reported that its superyacht segment took no orders in the first nine months of 2026.
Ferretti Gets 16,175 Square Meters of a Port Site That Burned in 2020
Ferretti Group’s concession covers Lot A of the former Tubimar site, 16,175 square meters. The Central Adriatic Sea Port System Authority is returning 37,030 square meters (about 398,600 square feet) there to shipbuilding in four lots, its president, Mirco Carloni, said in Ferretti’s announcement.
Carloni called the project a move “from the aftermath of the fire to the construction of the future.” Ferretti said the money will be spent over the next three years and the sheds will come into use in stages. The almost €30 million is about $32.9 million at the European Central Bank’s November 18 reference rate of $1.0968 to the euro, and the dollar figures below use the same rate. Chief executive Stassi Anastassov said in the announcement: “This is not expansion for the sake of expansion.” He thanked the port authority and the regional, municipal and maritime institutions for their support.
The sheds are aimed at steel and aluminum superyachts of 40 to 55 meters (131 to 180 feet), a size range where Ferretti said international demand is growing.
Clearing the site is the port authority’s job. It said on November 23 that demolition had started that morning under a 180-day contract worth €405,000 ($444,200), and that a second lot has gone to Palumbo Superyachts.
Ferretti’s Superyacht Segment Booked No Orders Through September
Ferretti’s Super Yachts segment recorded no order intake in the nine months to September 30, 2026, against €64.2 million ($70.4 million) from two contracts in the same period of 2025, according to the nine-month results the company published on October 27. The figures are unaudited.
The company as a whole kept taking orders. Group order intake was €664.9 million ($729.3 million) for the nine months, down 13.8%, and it rose 6.6% in the third quarter. Ferretti put the superyacht gap down to longer negotiations and wrote that none of its preliminary agreements had yet turned into an order. Anastassov named the superyacht business in that release as one of three areas where performance has to improve, along with the Americas and the Middle East, and said each has its own program.
The segment still has yachts on order. Its order backlog was €542.3 million ($594.8 million) on September 30, down 21.2% from a year earlier. Net backlog, which leaves out revenue already booked on those yachts, was €229.9 million ($252.2 million), down 43.9%. Ferretti said the Super Yachts and Made-to-Measure segments together keep a net backlog of more than €450 million. The results do not say which brands or yards make up the segment, so they cannot be matched line for line to the semi-custom metal yachts the new sheds are for.
The Announcement Gives No Hull Count, No Job Number and No Brand
Ferretti’s announcement does not say how many yachts a year the Ancona yard builds now or will build once capacity has doubled. It promises new employment and gives no number of jobs. It does not name the brands the five sheds will build, or the length of the concession.
Ferretti’s page for the yard lists nine construction sheds on 76,945 square meters (about 828,200 square feet), four of them for steel and aluminum yachts and five for the Custom Line range. The yard builds CRN, Riva’s superyachts, the Pershing 140 and Custom Line, and Ferretti puts its staff at more than 1,000.
A second project is already approved. The announcement said Ferretti has the first single authorization issued under Italy’s Special Economic Zone rules in Ancona’s port, to extend one shed so the yard can build superyachts up to 100 meters (328 feet). The port authority put that investment at €3 million ($3.3 million) on October 21 and said approval took 54 days.
Hullside’s Take
I don’t think the timing is the problem here. The first shed is not due until 2028, the segment has a backlog, and Ferretti says it has buyers in negotiation. A builder can reasonably plan new sheds in a slow year for orders. I do think the announcement asks the reader to take “double” on trust. Ferretti gave the investment, the number of sheds and the size of yacht, and it did not give the capacity that is being doubled or the jobs it expects to create, in a statement that thanks public institutions for their support. A supplier, a worker or a rival yard in Ancona needs those figures to judge the plan. I’ll report superyacht order intake when Ferretti publishes its full-year results.
Sources: Ferretti Group, Ferretti Group nine-month results, Central Adriatic Sea Port System Authority, European Central Bank, Trade Only Today