Quilcene's Boat Ramp Is Funded and Bid, but Crews Wait Until July 2027
Van Ness Construction bid $830,942 to rebuild the Herb Beck Marina ramp, and a September addendum moved in-water work to July 2027.
The Port of Port Townsend has picked Van Ness Construction to replace the boat ramp at Herb Beck Marina in Quilcene, Washington, the centerpiece of a $2 million overhaul that also rebuilds the parking lot and restroom. Port deputy director Eric Toews told the Port Townsend Leader in a story published November 25 that the project is fully funded, designed and permitted, and that he expects it to be finished next year.
In-water work at the ramp cannot start for almost eight months. The bid package the Port issued in August had crews starting in the water on October 1, 2026. A September addendum moved that start to July 15, 2027.
Port Revised the Work Window After a Bidder Flagged Conflicting Dates
The Port changed the schedule after a bidder pointed out that the drawings allowed in-water work until February 15 while the specification ended it on January 15, 2027. The Port’s reply, in Informational Bulletin No. 1 on September 3, was that the window had been revised in that day’s addendum.
Addendum No. 2 set the in-water work to start July 15, 2027 and end January 15, 2028, with substantial completion due by February 15, 2028 and physical completion by March 1, 2028. It also pushed the bid opening to October 2 and gave the contractor 90 calendar days from the notice to proceed.
A prospective bidder warned in Informational Bulletin No. 3 that the later start would add storage costs, and that the 60-day bid validity was pushing suppliers to raise prices. It recommended the Port delay the bid until early 2027. The Port told bidders to price the documents as issued and pointed to the contract’s clause on payment for stored materials.
The contract ties the window to the project’s permits. The Port Townsend Leader reported that the state limits in-water work in coastal zones to protect migrating salmon and other fish, and Toews said that puts construction in the fall and winter of 2027.
Van Ness Construction Came In 13% Under the Engineer’s Estimate
Three contractors bid when sealed bids opened on October 2, 2026. Van Ness Construction was low at $830,941.63 including 9.5% sales tax, against an engineer’s estimate of $952,655.48. Quigg Bros. bid $933,597.00 and Rognlin’s bid $1,046,250.60, according to the Port’s signed bid tabulation.
The Port’s bid results page lists Van Ness as the selected contractor as of October 8. The contract covers the water side only. Crews will tear out the old concrete ramp and its retaining wall, then lay a new ramp of precast concrete panels with a cast-in-place access wedge, a float landing, steel pipe piles and steel-frame boarding floats. The floats and piles are the largest line in the Van Ness bid, at $281,460.
The Port says on its Quilcene project page that the existing ramp “will soon be unsafe to use.” Kit Kittredge and Anne Ricker of the Linger Longer Improvement Committee, quoted in the Port’s 2022 grant presentation, called it “too steep, broken, rocky, and narrow.”
State Grant and Local Levy Each Pay About Half of the $2 Million
The money is split between Olympia and Jefferson County property owners. Toews said $1 million came through the state Recreation and Conservation Office in 2023, from its Boating Facilities Program. The other $1 million comes from the Port’s Industrial Development District levy, which county voters approved in 2019.
Those figures match the Port’s November 2022 grant presentation to the state, which put the total at $2,022,000 with $1,022,000 from the Port. It planned permitting for 2023 and 2024 and construction for 2024 and 2025. Reid Middleton, the engineering firm the Port selected after a 2023 request for qualifications, designed the ramp and floats, and Port engineering staff designed the upland work.
The new ramp will be wider and less steep than the old one, with an ADA-accessible concrete wedge and a handling float on its north side, the Port says. Toews said the back of the float can take temporary tie-ups, which frees several slips inside the marina for transient moorage. The upland work adds a resurfaced parking lot, picnic benches, a recycling center and a remodeled restroom.
Dredging the marina entrance is a separate project. The 2022 presentation estimated 10 to 12 feet of sediment build-up in places and a dredge of 1,700 to 2,000 cubic yards. The Quilcene page lists entrance dredging as a potential project under consideration and says that, at a minimum, the Port “will schedule a one-time dredge of the harbor entrance commensurate with the opening of the rehabilitated boat ramp.” Toews told the Leader that dredging is planned for 2029, pending funding.
Hullside’s Take
The Port should say whether the one-time entrance dredge on its Quilcene page still comes with the new ramp. That page links the dredge to the ramp’s opening, and the contract has the ramp substantially complete by February 15, 2028. My read is that a 2029 date, with no funding yet, means the new ramp opens onto the same silted entrance the Port measured in 2022. Jefferson County property owners are paying for half of this project through the levy, and they deserve a straight answer on whether the minimum dredge the Port wrote down is still the plan.
Sources: Port of Port Townsend (bid documents, bid tabulation, Quilcene project page, 2022 grant presentation), Port Townsend Leader, Washington State Recreation and Conservation Office